Top issues during term (9)(Roads)
I-15 Smart Freeway Pilot Results
The pilot cost $33 million over eight miles, far less than freeway widening at $10-100 million per mile.
Old Town Frog Parking program
$500,000 from the 2022 pandemic community reinvestment program.
Butterfield Stage Road Easement Acquisition (Closed Session)
Price and terms of the easement acquisition were under negotiation; amount unknown.
Citywide bike lane upgrades
Fully covered by an HSIP grant — no hit to the city's general fund.
All-way stop at Wolf Creek Drive North and Antelope Place
Local Roadway Safety Plan update
$134,585 plus a 10 percent contingency of $13,459.
ADA Curb Ramp Replacement Program
$334,000 contract, with up to $66,800 in authorized change orders.
Pauba Road Road Diet and Pavement Rehabilitation
The Paba Road project cost about $3.25 million.
Ynez Road Widening and Eminent Domain Easement
Roughly $4.5 million for about one-third mile of widening, funded in part by Measure S.
Decisions during term (0)
Recorded while Stewart was in office — not necessarily decisions they moved, spoke to, or voted on.
No decisions found matching Roads.
Voting record (0)(Roads)
No votes found matching Roads.