Summary
A hotel approved in 2018 near City Hall still hasn't been built. The council gave it two more years, but councilmembers pressed the applicant on the eight-year delay, incomplete funding, and steel beams left sitting on the property.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Aug 11, 2026.
Impact analysis
No direct city cost; the project's $1.2 billion-area tourism economy stands to gain hotel capacity and jobs when built.
The applicant gains two more years to secure financing for a project near Old Town's core.
Neighbors see a blighted site with stored steel beams and no construction progress for eight years.